Steel making plant Pohang steelworks |
 |
| |
A project to increase
annual production capacity to 4.65 million tons by improving compatibility,
cost saving, and the quality of the converter furnace operation via
the introduction of facilities with the same capacity as those of
Steel Work II for the purpose of enhancing the competitiveness of
the small steel-making plant at Pohang Steelworks. |
Project period: Jun. 2007 ~ Apr. 2010 |
Production capacity: 4.65 million tons/year |
Main facilities: 1 Dephosphorization(De-P) converter furnace,
1 Decarbonization(De-C) converter furnace |
Heat Size: 300 tons |
|
 |
Nitrogen
Splash Slag Coating facility for No.2
Steel making plant Gwangyang steelworks |
 |
| |
A facility for evenly
spraying the coating materials contained in slag onto the refractory
inside the converter furnace by blowing high-pressure nitrogen through
a lance after adding refractory coating materials such as soft-burned
dolomite to the slag remaining in the converter furnace after pouring
in melted iron from the furnace. This process ensures stable management
and extends the maintenance interval of the furnace to save costs.
|
Project period: May 2000 ~ Mar. 2001 |
Production capacity: 8.5 million tons/year |
Applied technology: Automatic control of nitrogen pressure
& flow rate, coating technique |
|